Important Milestone in the Construction of the Fehmarn Connection: The First of a Total of 89 Tunnel Elements has been Cast

Tunnelelement indefra

From Preparation to Execution – A Complicated Process

Patience is a virtue – especially when complicated designs, calculations, and processes must be transformed into reality.

Every beginning is hard, and the casting of the first element has indeed taken about 10 months, whereas it is expected that the elements can be produced in 9 weeks going forward.

“It has been a long and complicated task to cast such a large concrete structure, and it has now been demonstrated that technology and methods work well together,” says Henrik Vincentsen, CEO of Femern A/S in a press release.

Going forward, the elements can be cast at a completely different pace, precisely because meticulous data and know-how have been gathered in the process around the casting of the first element, and because all 5 production lines are now operational. Similarly, the casting process will be optimized as the workers accumulate more and more knowledge and experience.

A Great Achievement

There is also pride to be found at the executing consortium Femern Link Contractors (FLC) over the achieved milestone. “Casting a single tunnel element is a great achievement in itself, but we still have a long way to go. Nowhere else in the world are concrete elements of this size mass-produced, but that is exactly what we must master in the coming years. Our goal is to turn the exceptional into routine,” says FLC Director Sébastien Bliaut.

The fact that this is a GREAT achievement is emphasized by the size of each element. An element is 217 meters long, composed of 9 segments of 24 meters each. An element weighs 73,500 tons.

The Further Process

The finished element must now cure for 3-4 weeks before steel bulkheads and the ballast tanks that will ensure the element’s stability during submersion are mounted. Meanwhile, the production of the remaining 78 elements continues on 5 production lines, while a separate line produces an additional 10 special elements. According to the plan, the first tunnel element, to be mounted at the tunnel portal entrance, will be submerged later in the year.

New milestone reached on Storstrømsbroen: Landfast from both sides

storstrømsbroen-femern-belt-development

Tuesday, January 16 marked another milestone in the construction of the new Storstrøm Bridge, as the bridge became landfast from both Masnedø and Falster.

"Now the gap between the bridge deck on land and over water is closed, and we have a landfast bridge on both sides of Storstrømmen. It's a great start to the new year. Once the bridge sections are landfast, it will be much easier to transport materials and tools to the work sites. In the future, the contractor can drive it to the work site without being dependent on a boat, so the construction work will be both easier and faster," says Project Manager Niels Gottlieb, Danish Road Directorate.

Approaching the pylon in the middle of Storstrømmen

Since October 2023, the bridge has been land fast on Falster, and the bridge is constantly getting longer and approaching the pylon in the middle of Storstrømmen.

"After the New Year, bridge element 10-11S was hoisted up on the Falster side, so we got two new bridge elements up in the first half of January. I can not be anything other than satisfied with that," says Niels Gottlieb.

The new Storstrøms Bridge will open for car traffic in 2025 and for train traffic in 2027.

storstrømsbroen-femern-belt-development
This is what the new Storstrøm Bridge will look like. Visualisation: Vejdirektoratet